====== Gross/Net Times of the Reports ====== **Net time:** The time intervals of work performed in parallel are compared based on a priority order defined in the settings, and the time slice with higher priority overrides the one with lower priority (e.g., PC Time > Manually recorded Time). **Gross time:** All time spent on parallel work is taken into account in the report. Gross time also retains time entries that occur in parallel on the same task. **Gross time without duplicates:** The report only considers parallel work where entries were recorded for different tasks; in case of duplicates, netting is applied. By default, two reports in the system display gross time: the "Task time by day" and the "Project" reports. The "Dynamic workflow" report can display both Gross and Net time using a toggle. All other reports display Net time.