This is an old revision of the document!
Gross/Net Times of the Reports
Net time: The time intervals of work performed in parallel are compared based on a priority order defined in the settings, and the time slice with higher priority overrides the one with lower priority (e.g., PC Time > Manually recorded Time).
Gross: All time spent on parallel work is taken into account in the report.
Gross time also retains time entries that occur in parallel on the same task.
Gross time without duplicates: The report only considers parallel work where entries were recorded for different tasks; in case of duplicates, netting is applied.
By default, two reports in the system display gross time: the “Task time by day” and the “Project” reports.
The “Dynamic workflow” report can display both Gross and Net time using a toggle.
All other reports display Net time.